How Long Does It Take to Build a Pool?

How Long Does It Take to Build a Pool?

How Long Does It Take to Build a Pool?How long does it take to build a pool? Here at J&S Landscape in Boulder, it is the time of year when people think a lot about pools. If you want a new pool, we fully support such a great decision and can help you get yours installed. Given how quickly the long days of summer seem to go by, knowing how long a pool installation can take is an important consideration.

The following are general timetable guidelines. Your actual installation time can vary based on your individual circumstances. Be sure to talk to our J&S professionals for a better idea of the timeline needed for your pool size and design.

Design and Permitting

Estimating time for this stage can be very difficult. The design process often doesn’t take very long, though the more complicated your project, the longer the design process will be. The longer portion of this process is often the permitting. The turnaround time for a permit can depend on your local process and how busy those responsible are—after all, summer is a prime time to get projects done. For design and permitting, the process ranges from 1 to 8 weeks.

Excavation

After the design and permitting, excavation can be scheduled to begin work on installing your pool. Excavation can be as quick as a day or two but can take up to a week or more. Things that can affect the timing include ease of access, the location of utilities, and other variables. When it comes to how long does it take to build a pool, this is a bit of a wild card.

Electrical, Steel, and Plumbing

After the excavation takes place, steel is laid, electrical and plumbing are routed, and final checks are done for the final stages of constructing your pool. Part of this process includes making sure any additional water features are prepped, lighting is properly prepared, and any additional features are ready—spa addition anyone? Depending on the size and complexity of your pool project, this whole process can often be completed in 2 weeks.

Plastering, Fiberglass, Gunite, and Vinyl

Depending on the type of pool planned, this portion of the installation can take 1 to 3 weeks on average. Vinyl and fiberglass are faster to install while plaster and gunite will take longer. Any tile or additional pool decoration features may also add time.

Deck, Custom Features, and Landscaping

These final features are the last steps to making your pool the backyard addition you dreamed of having. These final stages allow for lighting to be completed, final custom touches to be added, and final landscaping work. Any other additions like decking, waterfalls, and added water features should be completed during this stage as well.

Total: Average of 6 to 10 weeks

For the final product and additional beautification, the time frame is really quite fast. Keep in mind that more complicated projects will take time. In the end, you will be satisfied and happy as you lounge in your cool pool water. If you want to know how long does it take to build a pool, contact us at J&S Landscape. We can install your pool and help you with all the additional elements your desire to make your pool space perfect.